Hamlets Electrification (HEP-IIB) — Lot 9, Mtwara Region

Ongoing Hamlets Electrification Project Phase IIB (HEP-IIB) Lot 9 in Mtwara Region (Contract No. TR198/2024/2025/W/04/9, Lot 9). Planned for completion in February 2029; 35% complete as at 30 April 2026.

Live status

Updated 30 Apr 2026
Progress 35%

Scope of work

  • 70 km of medium-voltage (MV) lines
  • 296 km of ABC low-voltage lines
  • 185 distribution transformers
  • 5,000 customer connections