Hamlets Electrification (HEP-IIB) — Lot 5, Rukwa Region

Ongoing Hamlets Electrification Project Phase IIB (HEP-IIB) Lot 5 in Rukwa Region (Contract No. TR198/2024/2025/W/04/5, Lot 5). Planned for completion in February 2029; 35% complete as at 30 April 2026.

Live status

Updated 30 Apr 2026
Progress 35%

Scope of work

  • 174 km of medium-voltage (MV) lines
  • 274 km of ABC low-voltage lines
  • 156 distribution transformers
  • 4,000 customer connections