Ongoing
Infrastructure
Hamlets Electrification (HEP-IIB) — Lot 5, Rukwa Region
Ongoing Hamlets Electrification Project Phase IIB (HEP-IIB) Lot 5 in Rukwa Region (Contract No. TR198/2024/2025/W/04/5, Lot 5). Planned for completion in February 2029; 35% complete as at 30 April 2026.
Live status
Updated 30 Apr 2026
Progress
35%
Scope of work
- 174 km of medium-voltage (MV) lines
- 274 km of ABC low-voltage lines
- 156 distribution transformers
- 4,000 customer connections