Ongoing Hamlets Electrification Project (HEP) Lot 11 in Mara Region (Contract No. TR 198/2023/2024/W/05, Lot 11). 93% complete as at 30 April 2026.
Live status
Updated 30 Apr 2026
Progress
93%
Scope of work
- 296 km of ABC low-voltage lines
- 148 distribution transformers
- 4,884 customer connections